Infrastructure, Mackney Brackernagh(Clancarty), Site A involves lands to the...
for Site A involving lands to the north east of Junction 15 on the M6 (east of Garbally Roundabout) and site B involving lands to the east of the R446, at an existing service station (Mackney, Ballinasloe). The proposed development will consist of: Site A (3.98ha) Provision of new electric vehicle charging hub for 36 vehicles...
The public decision state is shown, but conditions and later amendments can still change delivery scope.
Package signals below are limited to wording in the public application record.
No tender, award, contractor appointment, supplier appointment or procurement timetable is inferred.
What the public record evidences
Infrastructure
The public application record identifies infrastructure in the submitted planning scope.
Roads and site-development scope
The public application description explicitly references roads and site-development scope.
Services / drainage scope
The public application description explicitly references services / drainage scope.
Only source-supported scope signals are shown; generic trade padding is omitted.
Named source parties
- Promoter
- Petrogas Group Ltd
- Planning agent
- David Mulcahy
- Agent address
- 67 The Old Mill Race Athgarvan Newbridge Co. Kilare W12 X248
Application text
for Site A involving lands to the north east of Junction 15 on the M6 (east of Garbally Roundabout) and site B involving lands to the east of the R446, at an existing service station (Mackney, Ballinasloe). The proposed development will consist of: Site A (3.98ha) Provision of new electric vehicle charging hub for 36 vehicles (all under canopy measuring 3.22m high and including solar panels over) along with 4 no. EV HGV charging spaces (no canopy). Construction of single storey service station building (1,018.66sq.m) including net retail area of 100sq.m (excluding off-licence), 2 no. food offers, seating area, drive-thru hatch for one of the food offers, coffee dock, toilets, back of house area, along with external storage yard, outdoor play area and outdoor seating area. The maximum height is 11.08m high. All ancillary development including fuel pumps under canopy (5.6m high), underground tanks, vent pipes, HGV fuel pumps (6.7m high), new vehicular entrance off Garbally roundabout, new roundabout junction which will also facilitate future access to the lands to the north, car parking (83 – including staff, family and accessible spaces), cycle parking (16 no. spaces), HGV/Bus parking (13 no. – including 4 no. EV parking spaces), motor cycle spaces (5 no. spaces), drainage infrastructure (including SuDs measures), boundary treatments, hard and soft landscaping (including attenuation pond and bio-retention pond), internal roads, footpaths, dedicated active travel route along the northern boundary of the site from the east to west of the site, outdoor exercise and areas, outdoor picnic areas, brush and jet wash, single storey car wash plant building (12.5sq.m), roof mounted solar panels, signage (free standing [including totem sign] and on-building), single storey bin store (67.5sq.m), single storey substation building (38.23sq.m) and lighting. All associated site and drainage works. Site B (0.19ha) It is proposed to demolish all structures relating to the fuel element of the existing filling station (the fuel pumps, canopy, totem sign) and underground fuel tanks. The existing buildings containing the shop and storage will remain in situ. The car wash facility will be discontinued. A Natura Impact Statement is included with the application.
Application to site progress
-
Applied 11 Sep 2025 2561304
-
Decision Conditional 30 Jun 2026
-
Appeal No appeal indexed No public appeal record is indexed against this application.
-
Commenced No commencement indexed No reliable public commencement record is indexed against this permission.
-
Completed Completion not recorded Smaller works often do not require a completion certificate.
Source, scope and limits
Application description and scale 2561304
for Site A involving lands to the north east of Junction 15 on the M6 (east of Garbally Roundabout) and site B involving lands to the east of the R446, at an existing service station (Mackney, Ballinasloe). The proposed development will consist of: Site A (3.98ha) Provision of new electric vehicle charging hub for 36 vehicles (all under canopy measuring 3.22m high and including solar panels over) along with 4 no. EV HGV charging spaces (no canopy). Construction of single storey service station building (1,018.66sq.m) including net retail area of 100sq.m (excluding off-licence), 2 no. food offers, seating area, drive-thru hatch for one of the food offers, coffee dock, toilets, back of house area, along with external storage yard, outdoor play area and outdoor seating area. The maximum height is 11.08m high. All ancillary development including fuel pumps under canopy (5.6m high), underground tanks, vent pipes, HGV fuel pumps (6.7m high), new vehicular entrance off Garbally roundabout, new roundabout junction which will also facilitate future access to the lands to the north, car parking (83 – including staff, family and accessible spaces), cycle parking (16 no. spaces), HGV/Bus parking (13 no. – including 4 no. EV parking spaces), motor cycle spaces (5 no. spaces), drainage infrastructure (including SuDs measures), boundary treatments, hard and soft landscaping (including attenuation pond and bio-retention pond), internal roads, footpaths, dedicated active travel route along the northern boundary of the site from the east to west of the site, outdoor exercise and areas, outdoor picnic areas, brush and jet wash, single storey car wash plant building (12.5sq.m), roof mounted solar panels, signage (free standing [including totem sign] and on-building), single storey bin store (67.5sq.m), single storey substation building (38.23sq.m) and lighting. All associated site and drainage works. Site B (0.19ha) It is proposed to demolish all structures relating to the fuel element of the existing filling station (the fuel pumps, canopy, totem sign) and underground fuel tanks. The existing buildings containing the shop and storage will remain in situ. The car wash facility will be discontinued. A Natura Impact Statement is included with the application.
Open official record