New Application · decision due 5 Jul 2026Decision recorded

~13 dwellings, 3 Lyons Terrace, Finsklin Road, Sligo

Finsklin Road, Sligo · Sligo County Council · Plan 2660178 · PB ref PB-3547887579

The development is for alteration, renovation and extension to the existing hostel (Register Reference 46) including Change of Use to a residential housing development comprising of 9 no. single-storey one-bed apartments, 2 no. duplex one bed apartments and 2 no. duplex two-bed apartments (13 apartments in total). The proposal...

Indicative value Not listed PB indicative band
Units applied for 13 public application record
Floor area Not listed no reliable figure indexed
Decision due 5 Jul 2026 public planning date
Commenced None indexed public commencement index
Decision-stage scope

The public decision state is shown, but conditions and later amendments can still change delivery scope.

Application scope

Package signals below are limited to wording in the public application record.

Not procurement evidence

No tender, award, contractor appointment, supplier appointment or procurement timetable is inferred.

Application-stage scope

What the public record evidences

3 source-supported signals
Small multi-unit

Small multi-unit - 13 dwellings

The public application record identifies 13 dwellings in the submitted planning scope.

2660178Explicit application record
Site works

Roads and site-development scope

The public application description explicitly references roads and site-development scope.

2660178Explicit description signal
Services

Services / drainage scope

The public application description explicitly references services / drainage scope.

2660178Explicit description signal

Only source-supported scope signals are shown; generic trade padding is omitted.

Project facts

Named source parties

Promoter
Housing Association for Integrated Living
Planning agent
Ciaran O'Brien
Agent address
1 Johnson Place Dublin Dublin D02 HW58
Official description

Application text

The development is for alteration, renovation and extension to the existing hostel (Register Reference 46) including Change of Use to a residential housing development comprising of 9 no. single-storey one-bed apartments, 2 no. duplex one bed apartments and 2 no. duplex two-bed apartments (13 apartments in total). The proposal includes partial demolitions (modern outbuildings and sheds) and alterations. New, terraced two-storey and three-storey extensions with pitched roofs are proposed to replace the removed outbuildings. Site renewable energy measures are planned to include the provision of solar panels. New landscaping for amenity areas, pedestrian access with planted privacy buffers; common bike parking and bin storage. The development includes for connections to existing services (including existing mains drainage), temporary construction signage, new building signage, minor relocation of street lighting and all associated ancillary site development works

Source-aware chronology

Application to site progress

Empty lanes explain their state.
AppealsAn Coimisiún Pleanála
  1. Appeal No appeal indexed No public appeal record is indexed against this application.
CommencementPublic commencement index
  1. Commenced No commencement indexed No reliable public commencement record is indexed against this permission.
CompletionPublic completion projection
  1. Completed Completion not recorded Smaller works often do not require a completion certificate.
Evidence register

Source, scope and limits

Public planning record
Application description and scale 2660178

The development is for alteration, renovation and extension to the existing hostel (Register Reference 46) including Change of Use to a residential housing development comprising of 9 no. single-storey one-bed apartments, 2 no. duplex one bed apartments and 2 no. duplex two-bed apartments (13 apartments in total). The proposal includes partial demolitions (modern outbuildings and sheds) and alterations. New, terraced two-storey and three-storey extensions with pitched roofs are proposed to replace the removed outbuildings. Site renewable energy measures are planned to include the provision of solar panels. New landscaping for amenity areas, pedestrian access with planted privacy buffers; common bike parking and bin storage. The development includes for connections to existing services (including existing mains drainage), temporary construction signage, new building signage, minor relocation of street lighting and all associated ancillary site development works

AuthoritySligo County Council
Reference2660178
StatusChecked 29 Jul 2026