Commencement notice group

Housing commencement notices — Naas

Naas, Kildare

3 unique commencement events · latest notified commencement 29 Apr 2024 · planning references supplied

Unique commencement events
3
Latest notified commencement
29 Apr 2024
Latest notice
139 units
Planning references supplied
23/942 · PP22/221502
Public location
Naas, Kildare

Public source geography

Site location

Public site / locality
Naas, Kildare
County
Kildare
Approximate source location. Use the larger map if the inline map is unavailable.
Approximate source location — not an official site boundary Open larger map

Source meaning

What the commencement source confirms

A commencement notice records a declared building-control commencement date. It does not by itself confirm that every permitted work began or was completed.

Dates, scale and organisations below stay attached to the individual notice that supplied them.

Official sources

Official planning documents

Use the planning reference with the official register or the PlanningBrief council overview below.

These links are source-backed navigation. The notice-supplied planning reference remains separate from any verified canonical planning relationship.

Chronological source evidence

Commencement notice timeline

These records are grouped because they share the same planning authority and supplied planning-reference context. Each notice remains separate evidence; the grouping does not establish overall scheme scale, construction progress or completion.

CN0114915KE BCMS open-data feed

The development is for a new five storey apartment complex consisting of 3 blocks (A, B & C) connected by a landscaped first floor podium over ground floor undercroft car park between the 3 blocks. Block A will have 4 storeys and Blocks B & C will have 5 storeys. Block B contains a ground level commercial unit.

Work stated for this notice 139 units Explicit phase quantity stated by the source.

Floor area stated for this source: 28,599 m².

Planning reference 23/942 Planning reference PP22/221502
CN0003917KE BCMS owner-supplied export

The development is for a new five storey apartment complex consisting of 3 blocks (A, B & C) connected by a landscaped first floor podium over ground floor undercroft car park between the 3 blocks. Block A will have 4 storeys and Blocks B & C will have 5 storeys. Block B contains a ground level commercial unit.

Work stated for this notice Scale not stated for this notice.
Planning reference 23/942 Planning reference PP22/221502 Builder stated: Westar Investments Ltd Developer stated: Westar Investments Ltd
CN0111428KE BCMS owner-supplied export

Ground improvement Enabling Works for Harbour Gate, Finlay Park residential development, comprising Vibro- Stone Column piling only. Follow-on new apartment complex and podium to be under separate CN.

Work stated for this notice Scale not stated for this notice.
Planning reference 23/942 Planning reference PP22/221502 Builder stated: Westar Investments Ltd Developer stated: Westar Investments Ltd

A commencement notice records a declared building-control commencement date. It does not by itself confirm that every permitted work began or was completed. Future verified planning enrichment can be added to this record without changing its notice evidence.