New build
06 May 2019 · Latest notice
4 notices · phased
Dublin, Dublin · Dun Laoghaire Rathdown County Council · Planning ref P/1244/18
Soil removal and site clearance at Cherrywood Town Centre 4 at Cherrywood, Dublin 18.
Notice-stated scale
173 units · 48,552 m²
Notice-stated max
Highest notice-stated figure for each metric — notices are not summed.
Planning ref indexed
Builder not named
Notice identity Works stated Scale Commenced
SN0004170DR BCMS open-data feed
This application is for alterations to the construction of the shared basement / podium structure at Cherrywood TC2 development (approved FSC Reg Ref 18/8075), to include basement area previously omitted on commencement notice ref: 8417855, submitted, at TC2, Cherrywood, Dublin 18
16,665 m²Builder not named
06 May 2019
CN0048175DR BCMS open-data feed
Construction of 2-level shared basement / podium structure including 9 no.apartment units (level -1) as part of the phased construction to completion of TC2 Developments: Construction of new building: Two mixed use blocks situated over a shared basement; and all associated site development works including a shared hotel ramp, retail ramp access, shared attenuation tank and structure to Grand Parade at Cherrywood, Co. Dublin
9 units · 37,588 m²Builder not named
11 Feb 2019
CN0045568DR BCMS owner-supplied export
Soil removal and site clearance at Cherrywood Town Centre 4 at Cherrywood, Dublin 18
1 unit · 48,552 m²Builder not named
12 Nov 2018
CN0045592DR BCMS owner-supplied export
Soil removal and site clearance at Cherrywood Town Centre 4 at Cherrywood, Dublin 18.
173 units · 48,552 m²Builder not named
12 Nov 2018
The project row shows the highest notice-stated figure for each metric. Phases and notices are not added together.
New build
29 Apr 2019 · Commenced
1 notice · 1 source identity
Galway, Galway · Galway City Council · Planning ref LA/3/2018
Construction of 78 Residential units and associated site works at Ard Cre, Ballymoneen Road, Galway. Mix of terraced and semi- detached units - 19 apts, 19 duplex, 40 houses.
New build
26 Apr 2019 · Latest notice
2 notices · phased
Gort, Galway · Galway County Council · Planning ref 14-502 & 08-2336
construction of 18 houses (3 detached) (9 terraced) (6 semidetached) on sites 69 to 86 inclusive
Notice identity Works stated Scale Commenced
CN0051150GC BCMS owner-supplied export
construction of 18 houses (3 detached) (9 terraced) (6 semidetached) on sites 69 to 86 inclusive
127 units · 12,070.7 m²Builder named
26 Apr 2019
CN0049615GC BCMS owner-supplied export
9 house of a 120 unit development on sites 112 to 120 inclusive
120 units · 2,353.2 m²Builder named
11 Mar 2019
The project row shows the highest notice-stated figure for each metric. Phases and notices are not added together.
New build
16 Apr 2019 · Latest notice
3 notices · phased
Maynooth, Kildare · Kildare County Council · Planning ref 09/8
Construction of 15no. residential houses and associated works Carton Wood Maynooth Co Kildare.
Notice identity Works stated Scale Commenced
CN0050657KE BCMS open-data feed
Construction of 15no. residential houses and associated works Carton Wood Maynooth Co Kildare.
15 units · 2,039 m²Builder not named
16 Apr 2019
CN0046665KE BCMS owner-supplied export
Construction of 15no. residential houses and associated works Carton Wood Maynooth Co Kildare.
151 units · 2,039 m²Builder named
12 Dec 2018
CN0045215KE BCMS owner-supplied export
Permission for the construction of 2 storey creche and all associated works
514 m²Builder named
15 Oct 2018
The project row shows the highest notice-stated figure for each metric. Phases and notices are not added together.
New build
16 Apr 2019 · Commenced
1 notice · 1 source identity
Cabinteely, Dublin · Dun Laoghaire Rathdown County Council · Planning ref ABP PL06D.301614
Enabling works to site,including works to Brennanstown Road, alterations to the Brennanstown Road/Glenamuck Road North/Brighton Road/Claremont junction, connections to and through Cabinteely Park, site clearance & erection of hoarding associated with proposed 136 no. residential units (98 no. apartments and 38 no. houses), Creche facility at site at Brennanstown Road, Carrickmines, Dublin 18
New build
28 Mar 2019 · Latest notice
6 notices · phased
Wicklow, Wicklow · Wicklow County Council · Planning ref 16/1116
Phase 5 of residential development comprising construction of 7 no. new houses out of a total development of 35 no. new houses, and all associated site works, including provision of a new vehicular site entrance and all landscaping.
Notice identity Works stated Scale Commenced
CN0050375WW BCMS open-data feed
Phase 6 of residential development comprising construction of 7 no. new houses, out of a total development of 35 no. new houses, and all associated site development works, including provision of a new vehicular site entrance and all landscaping.
7 units · 647.5 m²Builder not named
28 Mar 2019
CN0048508WW BCMS owner-supplied export
Phase 5 of residential development comprising construction of 7 no. new houses out of a total development of 35 no. new houses, and all associated site works, including provision of a new vehicular site entrance and all landscaping.
35 units · 1,010 m²Builder named
15 Feb 2019
CN0046696WW BCMS owner-supplied export
Phase 4 of residential development comprising construction of 4 no. new houses out of a total development of 35 no. new houses, and all associated site works, including provision of a new vehicular site entrance and all landscaping.
35 units · 480 m²Builder named
13 Dec 2018
CN0045923WW BCMS open-data feed
Phase 3 of residential development comprising construction of 6 no. new houses out of a total development of 35 no. new houses, and all associated site works, including provision of a new vehicular site entrance and all landscaping.
6 units · 703.8 m²Builder not named
06 Nov 2018
CN0044964WW BCMS open-data feed
Phase 2 of residential development comprising construction of 4 no. new houses out of a total development of 35 no. new houses, and all associated site works, including provision of a new vehicular site entrance and all landscaping.
4 units · 469.2 m²Builder not named
12 Oct 2018
CN0043005WW BCMS open-data feed
Phase I of residential development comprising construction of 4 no. new houses out of a total development of 35 no. new houses, and all associated site works, including provision of a new vehicular site entrance and all landscaping.
4 units · 469.2 m²Builder not named
24 Aug 2018
The project row shows the highest notice-stated figure for each metric. Phases and notices are not added together.
New build
19 Mar 2019 · Commenced
1 notice · 1 source identity
Dunleer, Louth · Louth County Council · Planning ref 17309
The development will consist of (i) removal of remaining walls of stone building on site; (ii) provision of 80 no. residential units comprising: (a) 6 no. 4 bed units, (b) 37 no. 3 bed units, (c) 37 no. 2 bed units; (iii) renewable energy design measures for each housing unit; (iv) internal distributor road providing access to the site from the Ardee Road to the West with permanent fencing tot he south and temporary fencing to the North pending future development; (v) pedestrian access to the site from the Ardee Road to the South; (vi) ESB substation; (vii)varied site boundary treatment comprising walls and fencing; (viii) temporary signage; (ix) estate signage; and (x) all associated site works.
New build
11 Mar 2019 · Commenced
1 notice · 1 source identity
Allenwood Middle, Naas, Kildare · Kildare County Council · Planning ref 18/1203
Construction of 49 no. houses, consisting of 48 semi-detached 3 bedroom houses and 1 no. detached 3 bedroom house and all associated site development works.
New build
07 Mar 2019 · Latest notice
10 notices · phased
Dublin, Dublin · Dublin City Council · Planning ref 3069/14
The development will consist of Block C (27 apartments & 1 Retail Unit), Block D (19 apartments) over combined basement at Blocks C & D, Royal Canal Park, Pelletstown, Dublin 15
Notice identity Works stated Scale Commenced
CN0049060DC BCMS owner-supplied export
The development will consist of Block C (27 apartments & 1 Retail Unit), Block D (19 apartments) over combined basement at Blocks C & D, Royal Canal Park, Pelletstown, Dublin 15
46 units · 1,867 m²Builder named
07 Mar 2019
CN0048247DC BCMS owner-supplied export
Fit Out of Aldi Store in Block E Royal Canal Park
3,903 m²Builder named
11 Feb 2019
CN0033902DC BCMS open-data feed
The development will consist of Aldi retail Unit (Shell & Core Only)at Royal Canal Park, Ratoath Road, Pelletstown, Dublin 15
243 unitsBuilder not named
27 Nov 2017
CN0033973DC BCMS open-data feed
The development will consist of Block B (comprising 39 apartments and 1 retail units)at Royal Canal Park, Ratoath Road, Pelletstown, Dublin 15
39 unitsBuilder not named
27 Nov 2017
CN0021013DC BCMS owner-supplied export
Description of proposed development The development will consist of Block A (comprising 6 apartments and 2 retail units)at Royal Canal Park, Ratoath Road, Pelletstown, Dublin 15
6 unitsBuilder named
05 Oct 2016
CN0020923DC BCMS open-data feed
The development will consist of 71 houses at Royal Canal Park, Ratoath Road, Pelletstown, Dublin 15
71 unitsBuilder not named
04 Oct 2016
CN0013872DC BCMS open-data feed
The development will consist of 40 houses at Royal Canal Park, Ratoath Road, Pelletstown, Dublin 15
40 unitsBuilder not named
19 Feb 2016
CN0012195DC BCMS open-data feed
Single storey building comprising café, changing rooms and boat store at Royal Canal Park, Ratoath Road, Pelletstown, Dublin 15
1 unitBuilder not named
24 Nov 2015
CN0008191DC BCMS owner-supplied export
The development will consist of 1 house at Royal Canal Park, Ratoath Road, Pelletstown, Dublin 15
1 unitBuilder named
01 Jul 2015
CN0007724DC BCMS open-data feed
The development will consist of 40 houses at Royal Canal Park, Ratoath Road, Pelletstown, Dublin 15
40 unitsBuilder not named
09 Jun 2015
The project row shows the highest notice-stated figure for each metric. Phases and notices are not added together.
New build
06 Mar 2019 · Latest notice
2 notices · phased
Dublin 18, Dublin · Dun Laoghaire Rathdown County Council · Planning ref D17A/0793
Construction of a total of 12 no. apartments. The apartments will be provided within 1 no. four storey apartment block comprising of 8 no. 1 bedroom apartments and 4 no. 2 bedroom apartments, over an undercroft car park.
Notice identity Works stated Scale Commenced
CN0049024DR BCMS owner-supplied export
Construction of a total of 12 no. apartments. The apartments will be provided within 1 no. four storey apartment block comprising of 8 no. 1 bedroom apartments and 4 no. 2 bedroom apartments, over an undercroft car park.
24 units · 1,393 m²Builder named
06 Mar 2019
CN0038474DR BCMS open-data feed
Construction of 37 no. detached, semi-detached and terraced 2/3 storey houses, associated site development works and provision of a new vehicular access at Rockville House, Glenamuck Road, Dublin 18.
37 units · 4,810.8 m²Builder not named
08 May 2018
The project row shows the highest notice-stated figure for each metric. Phases and notices are not added together.
New build
25 Feb 2019 · Latest notice
2 notices · phased
Nenagh, Tipperary · Tipperary County Council · Planning ref 17601396
Construction of four new semi detached houses (two blocks of two)
Notice identity Works stated Scale Commenced
CN0048548TT BCMS owner-supplied export
Two new houses (No. 89 & 90) at Ciamaltha Meadows
69 units · 500 m²Builder named
25 Feb 2019
CN0048486TT BCMS owner-supplied export
Construction of four new semi detached houses (two blocks of two)
69 units · 2,000 m²Builder named
22 Feb 2019
The project row shows the highest notice-stated figure for each metric. Phases and notices are not added together.
New build
22 Feb 2019 · Latest notice
10 notices · phased
Lucan, Dublin · South Dublin County Council · Planning ref SDZ18A/0002
Construction of 55 Houses at Shackleton, Lucan Co. Dublin - 1-11 Shackleton Square, 28-37 Shackleton Drive, 1-12 Shackleton Abbey, 1-4 Shackleton Well, 1-10 & 22-23 Shackleton Cross and No's 1-6 Shackleton Manor.
Notice-stated scale
99 units · 447,347.3 m²
Notice-stated max
Highest notice-stated figure for each metric — notices are not summed.
Planning ref indexed
Builder not named
Notice identity Works stated Scale Commenced
SN0003940SD BCMS open-data feed
Construction of a three storey apartment / duplex residential building consisting of 7 No. ground floor apartments and 7 No. first floor duplex units at Shackelton View, Shackelton, Lucan, Co. Dublin
14 units · 1,425 m²Builder not named
22 Feb 2019
SN0003914SD BCMS open-data feed
Construction of a four storey apartment building consisting of 38 No. apartments and a two storey creche - Shackleton Mill, Shackleton, Lucan Co. Dublin. Note the creche is to be completed to shell and core stage only.
38 units · 3,830 m²Builder not named
20 Feb 2019
CN0046299SD BCMS open-data feed
Construction of 30 Houses at Shackleton, Lucan, Co. Dublin. 1-4 Shackleton Lawn, 11-21 Shackleton Cross, 1-10 Shackleton Vale & 23-27 Shackleton Drive.
30 units · 3,705.5 m²Builder not named
27 Nov 2018
SN0003449SD BCMS open-data feed
Block 4 - No's 1-4 Davis Hall, Shackleton, Lucan, Co. Dublin - a four storey duplex block containing 4 No. units.
4 units · 507 m²Builder not named
29 Aug 2018
SN0003451SD BCMS open-data feed
Block 5 - No's 1-4 Ross Gate, Shackleton, Lucan, Co. Dublin - a four storey duplex block containing 4 No. units.
4 units · 507 m²Builder not named
29 Aug 2018
SN0003452SD BCMS open-data feed
Block 6 - No's 1-4 Wilkes Court, Shackleton, Lucan, Co. Dublin - a four storey duplex block containing 4 No. units.
4 units · 507 m²Builder not named
29 Aug 2018
CN0041668SD BCMS open-data feed
Construction of 55 Houses at Shackleton, Lucan Co. Dublin - 1-11 Shackleton Square, 28-37 Shackleton Drive, 1-12 Shackleton Abbey, 1-4 Shackleton Well, 1-10 & 22-23 Shackleton Cross and No's 1-6 Shackleton Manor.
55 units · 7,166 m²Builder not named
23 Jul 2018
SN0003176SD BCMS open-data feed
Construction of Block No.1 - a four storey duplex block of 8 units - No's 1-8 Shackleton Mall, Shackleton, Lucan, Co. Dublin
8 units · 1,213 m²Builder not named
30 May 2018
SN0003177SD BCMS open-data feed
Construction of Block 2 - a three storey duplex block consisting of 12 No. units - 5-18 Shackleton Grange, Shackleton, Lucan, Co. Dublin
12 units · 1,484 m²Builder not named
30 May 2018
CN0038421SD BCMS open-data feed
The construction of 99 houses on lands at Shackleton, Lucan, Co. Dublin and all roads, infrastructure and site works associated with the permission as approved under register reference SDZ18A/0002.
99 units · 447,347.3 m²Builder not named
03 May 2018
The project row shows the highest notice-stated figure for each metric. Phases and notices are not added together.
New build
13 Feb 2019 · Commenced
1 notice · 1 source identity
Limerick, Limerick · Limerick City and County Council · Planning ref 157013
Construction of 11 no. 3 bedroom houses and associated entrance & site works.
New build
09 Feb 2019 · Latest notice
4 notices · phased
Loughrea, Galway · Galway County Council · Planning ref 14/237
Proposed construction of Phase 1 houses on previously constructed raft foundation for No. 1 to 21 and all associated site development work for 76 no. houses, creche and 2 commercial units.
Notice identity Works stated Scale Commenced
CN0048098GC BCMS owner-supplied export
Proposed construction of Phase 3 houses for No. 57 to 68 and all associated site development work for 76 no. houses, creche and 2 commercial units.
76 units · 3,115.2 m²Builder named
09 Feb 2019
CN0048053GC BCMS owner-supplied export
Proposed construction of Phase 1 houses on previously constructed raft foundation for No. 1 to 21 and all associated site development work for 76 no. houses, creche and 2 commercial units.
76 units · 15,308.6 m²Builder named
31 Jan 2019
CN0047062GC BCMS open-data feed
Proposed construction of phase 2 house no 22 to 56 including raft foundations and all associated site development work for 76 no. houses, creche and 2 commercial units
35 units · 73,899.4 m²Builder not named
15 Dec 2018
CN0043310GC BCMS open-data feed
Proposed site clearance and servicing including roadway's to 76 no.residential units, 2 no. commercial units and creche. Construction of Raft foundations to sites no. 1 - 21.
1 unit · 110 m²Builder not named
31 Aug 2018
The project row shows the highest notice-stated figure for each metric. Phases and notices are not added together.
New build
06 Feb 2019 · Latest notice
11 notices · phased
Navan, Meath · Meath County Council · Planning ref NA/170747
Construction of 71 No. two storey dwellings at sites 1-16 Cois Glaisin Green, 1-45 Cois Glaisin Heights, 27-29 (odd no only) and 31-38 Cois Glaisin Drive, Cois Glaisin, Johnstown, Navan, Co. Meath
Notice identity Works stated Scale Commenced
CN0048206MH BCMS open-data feed
Construction of 71 No. two storey dwellings at sites 1-16 Cois Glaisin Green, 1-45 Cois Glaisin Heights, 27-29 (odd no only) and 31-38 Cois Glaisin Drive, Cois Glaisin, Johnstown, Navan, Co. Meath
71 units · 7,620 m²Builder not named
06 Feb 2019
SN0004668MH BCMS open-data feed
Construction of a single storey creche at Cois Glaisin, Johnstown, Navan, Co. Meath
368 m²Builder not named
26 Dec 2018
CN0046272MH BCMS open-data feed
Construction of 43 No. two storey dwellings at sites 27, 29, 31, and 33 - 49 (Inclusive) Cois Glaisin Rise, 18 - 30 (even no only) Cois Glaisin Drive, and 17 - 32 (inclusive) Cois Glaisin Green Johnstown, Navan, Co. Meath.
43 units · 4,496 m²Builder not named
22 Nov 2018
CN0043341MH BCMS open-data feed
Construction of 30 No. two storey houses and associated site works at sites 2-20 (even numbers only) Cois Glaisin Drive, 27-43 (inclusive0 Cois Glaisin Walk and 28, 30 & 32 Cois Glaisin Rise, Johnstown, Navan, Co. Meath.
30 units · 3,068 m²Builder not named
31 Aug 2018
CN0038394MH BCMS open-data feed
Construction of 37 No. two storey houses and associated site works at sites 1-3 & 12-26 (even no. only) Cois Glaisin Rise, and 1-26 Cois Glaisin Walk, Johnstown, Navan, Co. Meath
37 units · 3,446 m²Builder not named
04 May 2018
CN0038400MH BCMS open-data feed
Construction of 4 No. two storey houses and associated site works at sites 10 & 11, and 23 & 25 Cois Glaisin Rise, Johnstown, Navan, Co. Meath.
4 units · 436 m²Builder not named
04 May 2018
CN0038841MH BCMS owner-supplied export
Construction of 6 Communal Bin Store enclosures for dwellings located in Phase 2 of a residential development at Cois Glaisin, Johnstown, Navan, Co. Meath.
6 units · 60 m²Builder named
23 Apr 2018
CN0037460MH BCMS open-data feed
Construction of 11 no. two storey houses and associated site works at sites 4 to 9 (inclusive), and 13 to 21 (odd numbers only) Cois Glaisin Rise, Johnstown, Navan, Co. Meath.
15 units · 956 m²Builder not named
24 Mar 2018
CN0035621MH BCMS open-data feed
Construction of 13 no. two storey houses and associated site works at sites 12-22 (even no. only), and 23 to 29 (inclusive) Cois Glaisin Lawn, Johnstown, Navan, Co. Meath.
13 unitsBuilder not named
05 Feb 2018
CN0034045MH BCMS open-data feed
Construction of 13 no. two storey houses and associated site works at sites 12-24 (even no. only) and 25-29 Cois Glaisin Lawn.
13 unitsBuilder not named
01 Dec 2017
CN0034157MH BCMS open-data feed
Construction of 31 No. two storey dwellings amd associated site works and landscaping at sites 2-10 (even no. only) Cois Glaisin Avenue, 1-19 (odd numbers only) and 21-36 Cois Glaisin Court
31 unitsBuilder not named
30 Nov 2017
The project row shows the highest notice-stated figure for each metric. Phases and notices are not added together.
New build
05 Feb 2019 · Latest notice
12 notices · phased
Drogheda, Louth · Louth County Council · Planning ref 16231
Constrution of 3 blocks of Duplex apartements consisting of 16 units in total and all associated ancillary site work.
Notice identity Works stated Scale Commenced
CN0048151LH BCMS owner-supplied export
Constrution of 3 blocks of Duplex apartements consisting of 16 units in total and all associated ancillary site work.
50 units · 1,814.1 m²Builder named
05 Feb 2019
CN0046468LH BCMS open-data feed
Construction of one block of four terraced houses (4 Units) and all associated ancillary site works.
4 units · 335.8 m²Builder not named
04 Dec 2018
CN0046271LH BCMS owner-supplied export
Construction of two blocks of four terraced houses (8 units) and all associated ancillary site works.
20 units · 640 m²Builder named
27 Nov 2018
CN0044861LH BCMS owner-supplied export
Construction of one block of four terraced houses (4 Units) and all associated ancillary site works.
105 units · 335.8 m²Builder named
17 Oct 2018
CN0044244LH BCMS open-data feed
Construction of three blocks of three terraced houses (9 Units) and all associated ancillary site works.
9 units · 797.3 m²Builder not named
27 Sep 2018
CN0039935LH BCMS owner-supplied export
Construction of Block 6, Rampart Green, consisting of 1 two bedroom terraced house and 2 three bedrooms terraced houses and all associated ancillary site work.
80 units · 291.8 m²Builder named
11 Jun 2018
CN0035983LH BCMS owner-supplied export
Construction of Blocks 5 and 17 comprising of 7 of a total of 105 dwelling units (two and three storeys in height) and all associated site works.
105 unitsBuilder named
13 Feb 2018
CN0035420LH BCMS owner-supplied export
Construction of Blocks 21 & 22, comprising 12 of the total 105 dwelling units (two and three storey in height) and all associated site works.
105 unitsBuilder not named
01 Feb 2018
CN0035375LH BCMS open-data feed
Construction of block 14 comprising of 8 of a total of 105 dwelling units (two and three storeys in height) and all associated site works
8 unitsBuilder not named
31 Jan 2018
CN0035392LH BCMS owner-supplied export
Commencement of Blocks 15-16 encompassing 12 units of the total 105 dwelling units (two and three storeys in height) and all associated site development works.
105 unitsBuilder named
31 Jan 2018
CN0034915LH BCMS owner-supplied export
Construction of 105 dwelling units (two and three storeys in height); All associated site development works including the construction of
105 unitsBuilder named
08 Jan 2018
CN0030416LH BCMS owner-supplied export
Construction of 105 dwelling units (two and three storeys in height); All associated site development works including the construction of circa 360 metres of rising main across St. Dominic`s Park between the application site and Rathmullan Road, connection to the existing public sewer on the Rathmullan Road, landscaping, open space, boundary treatments, roads, footpaths, car parking, public lighting and services; Vehicular and pedestrian access off the Rathmullan Road.
105 unitsBuilder named
03 Aug 2017
The project row shows the highest notice-stated figure for each metric. Phases and notices are not added together.
New build
14 Jan 2019 · Commenced
1 notice · 1 source identity
Parnell Street, Dublin · Dublin City Council · Planning ref LAW 3985/16
Mixed use development comprising 72 dwellings, car parking spaces, a community centre and commercial space on Lower Dominick Street
New build
03 Jan 2019 · Commenced
1 notice · 1 source identity
Dublin, Dublin · Fingal County Council · Planning ref F18A/0205
Construction of 63 Houses (42-104 Cedarview, Northwood, Santry) Permitted under Reg. Ref's F15A/0440, F17A/0371 & F18A/0205 and all ancillary site development works.
New build
07 Dec 2018 · Latest notice
3 notices · phased
Ashtown, Dublin · Dublin City Council · Planning ref 3604/12
Phase 3 of development at Rathborne Park, consisting of 13 No. terraced housing units and all associated site works, as part of development granted under planning ref: 3604/12
Notice identity Works stated Scale Commenced
CN0046738DC BCMS owner-supplied export
Phase 3 of development at Rathborne Park, consisting of 13 No. terraced housing units and all associated site works, as part of development granted under planning ref: 3604/12
62 units · 1,391 m²Builder named
07 Dec 2018
CN0036727DC BCMS open-data feed
Phase 2 of development at Rathborne Park, consisting of 73 No. housing units and all associated site works, commencing as part of 208 No. dwellings, a creche (plus associated outdoor playing area) and two 5-a-side playing pitches granted under planning ref: 3604/12
73 unitsBuilder not named
12 Mar 2018
CN0033778DC BCMS open-data feed
Phase 1 of development at Rathborne Park, consisting of 60 No. housing units and all associated site works, commencing as part of 208 No. dwellings, a creche (plus associated outdoor playing area) and two 5-a-side playing pitches granted under planning ref: 3604/12
60 unitsBuilder not named
22 Nov 2017
The project row shows the highest notice-stated figure for each metric. Phases and notices are not added together.
New build
28 Nov 2018 · Commenced
1 notice · 1 source identity
Mulhuddart, Dublin · Fingal County Council · Planning ref PART XI/004/17
Ladyswell Square: Residential development of 65 dwellings comprising 43 houses and 22 apartments, with associated site development and external works including access roads and landscaping.
New build
09 Nov 2018 · Commenced
1 notice · 1 source identity
Barraduff, Kerry · Kerry County Council · Planning ref 05/2462
Construction of 91 houses onto the existing housing estate at Barraduff, Co. Kerry
New build
22 Oct 2018 · Latest notice
2 notices · phased
Cabinteely, Dublin · Dun Laoghaire Rathdown County Council · Planning ref D16A/0343
Construction of Apartment Blocks C & D within Carraig Bui Residential Development
Notice identity Works stated Scale Commenced
CN0044996DR BCMS owner-supplied export
Construction of Apartment Blocks C & D within Carraig Bui Residential Development
28 units · 3,708 m²Builder named
22 Oct 2018
CN0036449DR BCMS open-data feed
Residential development of 48 no. dwellings comprised of 20 no. houses and 28 no. apartments. The proposed development consists of: (i) 12 no. 4 bedroom 2-3 storey semi-detached houses, (ii) 4 no. 5 bedroom 2-3 storey semi-detached houses, (iii) 4 no. 5 bedroom 3 storey semi-detached houses and (iv) 28 no. 1, 2, and 3 bed apartments in 2 no. 5 storey apartment buildings, with semi-detached car parking provided for under one of the buildings. Access to the proposed development is via an existing access delivered under a previously permitted development Reg. Ref.s PL06D.111754 and D97A/0883. The proposed development also includes all associated site development and infrastructure works, surface and semi-basement car parking, open spaces and landscaping, all on a site area of 1.14ha.
20 unitsBuilder not named
06 Mar 2018
The project row shows the highest notice-stated figure for each metric. Phases and notices are not added together.
New build
10 Oct 2018 · Latest notice
5 notices · phased
Lucan, Dublin · South Dublin County Council · Planning ref SDZ16A/0005
Somerton Phase 1.4 - Construction of 46 Units as part of overall development of 246 units under Planning ref SDZ16A/0005, ammended under SDZ18A/0006.
Notice-stated scale
91 units · 7,238.7 m²
Notice-stated max
Highest notice-stated figure for each metric — notices are not summed.
Planning ref indexed
Builder not named
Notice identity Works stated Scale Commenced
CN0045227SD BCMS open-data feed
Somerton Phase 1.4 - Construction of 46 Units as part of overall development of 246 units under Planning ref SDZ16A/0005, ammended under SDZ18A/0006.
46 units · 5,424.6 m²Builder not named
10 Oct 2018
CN0041480SD BCMS open-data feed
Somerton Phase 1.3
54 units · 7,238.7 m²Builder not named
19 Jul 2018
CN0036650SD BCMS open-data feed
1,3,5,7,9,11,13,15,17 Somerton Copse, 15,17,19, Somerton Avenue, 2,4,6,8,10,12,14,16 Somerton Lawns, 10,12,13,14,15,16,17,19,21,23,25,27 Somerton Way, 6,7,8,9,10,11,12,13 Somerton Crescent and all associated site works.
40 unitsBuilder not named
12 Mar 2018
CN0032583SD BCMS open-data feed
1,3,5,7,9,11,13-19,21,23,25,27,29,31,33 Somerton Green, 1-16,18,20,22,24 Somerton Grove, 14,16,18,20-29,31,33,35,37,39,41,43,45,47,49,51 Somerton Avenue, 1-11 Somerton Park, 14&15 Somerton Crescent, 29&31 Somerton Way, 2,4,6,8,10,12,14,16,18,20,22,24 Somerton Copse and all associated site works.
91 unitsBuilder not named
13 Oct 2017
CN0029627SD BCMS open-data feed
17,19,21,23,25,27 Somerton Grove, 02,04,06,08,10,12, Somerton Green, 33,35 Somerton Way, 16 Somerton Crescent and all associated site works. Constructed as part of 177 No. residential units granted under planning ref: SDZ16A/0005
15 unitsBuilder not named
17 Jul 2017
The project row shows the highest notice-stated figure for each metric. Phases and notices are not added together.
New build
01 Oct 2018 · Latest notice
2 notices · phased
Enniscorthy, Wexford · Wexford County Council · Planning ref 20171337
Phase 2 - Erection of 14 No dwelling houses (part of overall development of 28 dwelling houses)
Notice identity Works stated Scale Commenced
CN0047064WX BCMS owner-supplied export
Phase 2 - Erection of 14 No dwelling houses (part of overall development of 28 dwelling houses)
28 units · 18,258.8 m²Builder named
01 Oct 2018
CN0037553WX BCMS open-data feed
Erection of 14 No dwellings houses - Phase 1 (part of an overall development of 28 dwelling houses comprising of 25 No two storey houses and 3 No single storey houses and associated site works)
14 units · 18,320.4 m²Builder not named
28 Mar 2018
The project row shows the highest notice-stated figure for each metric. Phases and notices are not added together.
New build
17 Sep 2018 · Commenced
1 notice · 1 source identity
Clondalkin, Dublin · South Dublin County Council · Planning ref SD168/0007
63 newbuild dwelling houses at St Cuthberts Park, Lealand Road, Deansrath, Clondalkin, Dublin 22 with associated siteworks.